Validating Software used for the Pharmaceutical Industry                                                                             

 

The Validation SOP and the Required Documentation

Since you are looking at this web site you either work for a Pharmaceutical corporation or a contract research organization (CRO).  You or your company may have just created or purchased a program or computerized system.  You should be congratulated on your hard work and creativeness for taking this system from inception to the production stage.  For this initiative you will now be punished.  You see if this system helps contribute to a regulatory submission (submission to the American Food and Drug Administration [FDA], European Agency for Evaluation of Medicinal Products [EMEA] or any other international agency) the system has to be validated.  I am going to describe to you what is involved with validation and the steps needed to carry out validation of your system by helping you create a validation Standard Operating Procedure (SOP).  In other words, we will create an SOP which will guide you through all the steps that must be preformed to validate your system.

Before we do anything, you first need to raise your right hand and say this out load, "I am reading this for informational purposes and I understand that by following the instructions laid out in this document the author does not guarantee that the validation documents produced will pass an audit by the FDA, international regulatory agency or a client."  In other words don't blame me if your validation package doesn't pass an audit.

Why did I create this instructional web site?  I want people to know that validation can be done in-house and I want to give people a plan to follow that will result in a successful and defensible validation package.  

One thing to remember before we start, validation is costly and time consuming but in the end it is much cheaper then failing an audit.

 

The Validation SOP

Write a Standard Operating Procedure (SOP) which describes your validation process. 

The SOP will serve as a guide for you to carry out the validation.  By writing the SOP you will have two essential items:

  1. The SOP itself which you must show to an auditor
  2. Templates will be created that will be used to structure your validation process. 

Remember an auditor will look at your validation SOP and compare it with the documents produced during validation (validation package). The auditor will be looking to see that you followed what is written in the SOP.  Also, remember no matter who does the validation (you or a contractor) it can take time.  It is better to do a thorough validation the first time then have to redo because it failed an audit.

__________________________________________________________________

Part 1 - each of the following sections should be addressed in the SOP

A. Purpose of the SOP

The SOP should start out with the purpose of the SOP.  This is relatively straight forward. The purpose of such an SOP is "To describe the process by which you validate systems." Also include this definition, "Validation insures that a system is suitable for its intended purpose and that it meets the standards set by the FDA or EMEA."

 

B. Importance of creating a validation SOP

It is important because of the following reason:

 A regulated system helps in the collection or analysis of clinical data that is used to decide whether a drug, medical device or procedure is efficacious. A system that is error prone may distort the data thus making a decision on the effectiveness of the drug, device or process inaccurate.  Always think what is the level of risk when this system is used.  Any system that collects data during a clinical trial or is involved in the manufacture of a drug, vaccine, medical device is high risk and deserves an extensive validation. 

 

 

 C. Audience

State who in the company should read and understand this SOP.  List the job titles of people and their department who should know this SOP.  Don't list people's names. A validation SOP is usually of importance to the Quality Control (QC) staff, staff that created and maintains the system, project managers, supervisors, company officers and statisticians.  This list is totally dependent on the way your company is structured. 

 

D. References

List documents that you cite in this SOP.  For example if you work in the United States you have to cite 21 CFR 11 and/or ICH validation documents.  If you do not know what these documents are then look them up on the FDA and EMEA web sites.  Then reference any other corporate SOP that you will cite in this validation SOP.  At the end of writing this SOP make sure you reference all appropriate documents, and check that you do not reference a document that is not mentioned in the text of the SOP.

 

 E. Definitions

List acronyms and their definitions and any technical words that you feel need further explanation.  Define only acronyms and technical terms used in the document.  For example the following could be defined in a validation SOP:  validation, SOP, QC, test plan, etc..)

 

F. Validation Goals

What do you intend to achieve by following this SOP and what do you intend to produce as output during a validation process

  • achieve:  You intend to create an SOP that if followed will certify that a system works according to the requirements set forth in the requirements document.  This SOP will define standardized validation procedures that can be applied to any regulated system that is produced
  • produce: Here is where you introduce the output that will make up you validation package.  The validation package is a documentation package that covers every step from design, testing, certification, deployment and retirement.  Basically the documents reflect a complete system life cycle. Listed below is what is expected in a validation package and each will be addressed in section 2.
  1. Initiation of validation effort - Validation is an expensive and time consuming effort, a document should be produced certifying that specified parties agree validation is needed and provide the reason it is needed.
  2. System Requirements - What the system is supposed to do
  3. Design document - How the system will do the tasks specified in the requirements
  4. Validation Plan - Steps in validation; who will carry them out and how the system will be tested.
  5. Testing materials - This is primarily made up of the operational qualifications, performance qualifications (test scripts), and the installation qualifications which describes how the system was installed on your test bed (test server) and how you proved it was installed correctly.  I will discuss this in detail later.
  6. Test results and approval of testing (test summary report)
  7. Validation summary report - Overview of validation, mention any deviations from original validation plan and final certification 

Remember you will need templates for all of these documents (with the exception of the test script) and the templates should be attached as amendments to the SOP (see Appendix A).

 

 

 __________________________________________________________________________________________

Part 2

Now we come to the part of the SOP where we describe the procedures in detail.  When people write an SOP they tend to get carried away and attempt to create the perfect SOP.  What happens is that they propose procedures and documentation so complex and cumbersome that they cannot be carried out. The result is that the actual validation process does not follow the SOP.  The auditor sees this and has a wonderful time writing up all the places you did not follow your own SOP.  Now you have to go back and re-write your SOP and then document to the FDA, EMEA or your client all the corrective actions you have taken. BE REALISTIC, REMEMBER ALL YOU WANT TO DO IS DOCUMENT THE SYSTEM AND THEN TEST THE SYSTEM TO MAKE SURE IT WORKS, that is the function of validation.  Large pharmaceutical firms can write grandiose validation SOPs and can pay a contractor to carry them out, small pharmaceutical companies and CROs need to be realistic.  Create a logical SOP, that when followed validates a system. Do not write something that you do not have the resources to carry out.  

In this section you may notice I get carried away and start telling you not only what should be in the SOP, but give advice on how to write the validation package and carry out validation.

A. Initiation of Validation

This is a document that states that the corporate officers and the QC manager have agreed that validation of a system is warranted. It should also provide a reason why it is warranted.  This reasons could be the following

  • A new system has been created
  • A new system has been purchased and validation is required to make sure it meets the company's needs
  • A system has been modified to such a degree that the entire system must be revalidated

This can even be an e-mail to the QC department, that is initiated by the corporate officers or member of the information technology (IT) department stating that validation is needed.   It can also be notes from a meeting that results in a decision that a system must be validated.

 

 

B. The Requirements

The requirements is a document which organizes all the functions that the system has to perform. This document is created for two reasons. First, to document all tasks the users needs the system to perform and secondly, to communicate these requirements to the system designers and programmers. 

 The issues below should be dealt with in the SOP

Mention that the document is divide into functional areas such as security, administration functions, user functions (data entry, data importation, data analysis, sampling) and report generation.  In the actual requirements document for each of these areas provide a detailed breakdown of the functions. For example, under security you should address how the users logs on to the system by entering a username and password.  You then address how the system handles the situation when a person continues to enter the wrong password.  The SOP should mention the methods used to write the requirements.  The requirements document should be done in a manner that is easy to modify.  People will want to add new requirements at all phases of the development process.  Use a spreadsheet or software created for documenting requirements.  Mention in the SOP that you number the requirements so you can eventually map these requirements to the tests in the test script.

 

If you purchase a system (Commercial Off The Shelf, referred to as COTS) there are two approaches to documenting the requirements.  In the SOP you can state COTS requirements may be dealt with as follows:

1.      The requirements document created by the company that created the system will be requested.  The company may or may not provide this documentation.  In any case you must show evidence that you requested this document from the creator of the system.

2.      Write your own requirements based on what you need the COTS software to do.  The software purchased may do more then what is needed.  In that case only document the requirements that you need.

3.      If the manufacturer sends you their requirements document you may edited them down to reflect how you use the software

By mentioning all these options in your SOP you are leaving many options opened to you in how you deal with requirements related to COTS software.

The requirements document must be approved.  This usually is the responsibility of the QC manager, the staff members who requested the software and others depending on corporate structure. Describe your approval process for the requirements.

 

C. The Design Document

The system analyst takes the requirement document and creates a design which is used as a guide by the programmers.  The programmers then write the source code based on the design. Creation of a system design can be done using many tools and techniques.  This document can be a combination of text, graphics (flow charts, relationship diagrams, etc..), table structures and mock reports. This document should mention what software tools will be used to create the system (i.e. Oracle, Delphi, C.net, Visual Basic.net, etc..)

The design document for a COTS system should be provided by the creator of the software. State this in your SOP. If the supplier of the software will not provide the design document you must show evidence that you requested this document. Most likely the manufacturer of COTS software will consider it proprietary and will not provide it to you. In the actual validation package mentioned when you requested the design document and the response you received from the manufacturer and when the response was received.

The design document must be approved by QC, a representative of the IT department who will use the design to base their programming and corporate officers.

 

 

D. The Validation Plan

This is the heart of the validation package it is going to describe the processes used to prove that a system is doing what it is supposed to do. The validation package should contain the following:

  1. Description of the system - This should be a short description of the system and constitutes the first part of the validation plan template.

2.      Risk assessment - This describes how critical it is that the system performs correctly.  Since this system is involved in creating a portion of a submission to the FDA, European or Asian regulatory agency, the level of risk is high.  The risk must be addressed, but in reality you would not validate a system that was unimportant, so the level of risk is always high. The risk is high because if the data is distorted in any way it could effect the decision whether or not the product is efficacious or safe. (See section 2 of the validation plan template - Appendix A). 

3.      Actions that will be carried out to validate the system

                    a. Specify the actions - (i.e. developing requirements, writing test script, etc.)

                    b. Who will perform the task (specify the type of person - software tester,

                         programmer) Remember you need someone to write the requirements, plus people

                        who will use the system will need to be interviewed in order to understand all the

                         requirements needed. You will need a person to create a design,

                        someone to program, someone to write the test script,

                        someone to install the system in the test bed and make sure it is installed correctly, a

                        software tester, a technical writer to write the user manual and a trainer to train

                        people to use the system.  If you have purchased a system fewer people are

                        needed because there are fewer tasks to carry out.

                    c. Estimated time to completion - A time line is of limited use.  Mention in the SOP that this is

                       only an estimate. 

               

  4. List all deliverables that will be produced

                   a. Requirements

                   b. Detailed systems design

                   c. Validation Plan

                   d. Installation Qualifications - How system was installed in the test bed and how success

                       was determined

                   e. Operational Qualifications/Performance Qualifications - The complete set of test scripts and

                       result of each test.

 

                        Sometimes the operational qualifications will just involve making sure that all the primary

                        modules are activated after the IQ.  The more detailed testing is often referred

                        to as performance qualifications (PQ).  The OQ and PQ are most often divided up

                        when the OQ is performed immediately after the IQ.  The PQ then extensively tests all

                        operations of the application and it will overlap to some extent with what was tested in the

                        OQ.

 

                        When you create your own software there may be no need to create both a OQ and PQ,

                         since you have been testing the software throughout its development, and should be

                         confident that your IQ worked.  This though is up to the development team and the QC

                         department.  For COTS software I would always create a separate OQ and PQ, because

                         you will not be that familiar with the software and after the IQ is carried out you will want

                         to know as soon as possible if the basic functions of the system are functional.

                        

                   f. Requirements/Testing traceability matrix  - Maps a specific requirement or

                      requirements to a specific test script.

                   g. Test Summary Report - Overview of the results of the testing

                   h. Validation Summary - Overview of validation includes approvals

                   i. Deviation Report, if necessary - What didn't go as planned and corrections made

 

5. How will these documents be controlled

     This falls under the domain of configuration management.  Configuration management should be a

     separate SOP.  Basically it consists of version control and naming conventions.  For the

     validation plan you just want to mention how the documents will be stored.  Also mention

     programming code control.  Code control involves using a software tool or procedure so two

     people aren't changing the code at the same time.  There are many software tools that can be

     purchased that can handle this job. Finally, if the version of the system changes what naming

     convention will be used.  I recommend putting most of this in a separate configuration

     management SOP and just referring to this SOP.  Also it is best to purchase a version control

     system that checks source code modules in and out.  Version control software is also valuable

     for controlling documents.

 

6. Testing Approach

     In this section you will describe how your testing will be carried out.  First give an overview of

     testing.  Will it be done in a modular fashion?  If you are testing after modifying the system will

     there be selective retesting of the system (regression testing). Describe how the test scripts

     will be written.  How an error found during testing will be handle.  How the error will be

     investigated and corrected and how the resulting re-testing will be done and tracked.  If test

     data files need to be created describe how they will be created.

 

 7. Quality Control Measures  

     This section will list what steps the QC staff will take to insure all documents are written

     correctly and are approved.  This should include a description of how QC staff will go over

     documents making sure all documents are created in the correct temporal order (i.e. test scripts

     should not be written before the requirements and design document).  Here you are specifying

     how validation activities will be checked.  The QC staff should be monitoring all documents as

     they are created so there are no surprises.  One area that QC should pay particular attention

     to is dates.  Make sure when someone signs and dates something the dates make sense.  For

     example the date certified that a test was carried out should not be prior to the date the test

     script was created.  Auditors are always on the look out for date problems.

 

8. Training that will be implemented

     If you are implementing a new system it will require training the users.  This is also true even

     if the old system is undergoing extensive modification.  Describe in the SOP how your company

     will decide what training is needed and how the training will be implemented.

     For example, if you have a staff trainer how will that person become familiar

     with the new system or modifications to an existing system. Once again do not make it so

     specific or complex that you cannot carry it out.  For example, do not state that you will

     write a complete set of manuals when your company does not have any technical writers

     on the staff or the budget to carry out such a task.

 

9. Approvals

    This contains the dated signatures of the people responsible for approving the plan.  These

    signatures are obtained before the plan is implemented.  Their signatures indicate that the plan is

    sufficient and and by approving it you now have permission to carry it out.  Declare in the SOP who

    should sign the document (there should be a submitter, reviewer(s), approvers).

 

 

E. Test Summary Report

The template in Appendix A can act as an outline for what should go into the Test Summary Report portion of the  SOP.  You are going to describe what you did to test the system.  This should match what was stated in the validation plan in the Testing Approach section. Divide this part of the SOP into the following sections and in the SOP describe what each of these sections will be used for.

1.      Testing environment: This is the document where you describe your testing set up.  In the real validation package it will say something like, a COMPY 386 server was used as the test bed for the front end of the application, while a LapLink 360 server was used to support the database.  The server was located at the StrongBad Corporate headquarters.  Testing was carried out after the installation qualifications (IQ) were successfully carried out.  This is about all the information you need.  The IQ document will contain the detailed steps that were followed to actually install the system.

2.      Testing documents created:  This test summary report should just list the testing documents created

                While this may not be the perfect place to discuss this I will describe what should go into

                each of these documents in a real validation package

                a.  Installation Qualification: Steps to install application on test bed.  In this document after

                    each step a check box should be displayed indicating if the step was carried out

                    successfully or unsuccessfully.  The installer should initial each step indicating who

                    carried out the step.  At the bottom of the IQ document the installer should sign

                    and date the document. In addition a verifier (person who attests that the installation

                    was successful) should sign and date the document.  If the system has a front end (user

                    interface) and a backend (database) you should start by describing how the backend

                    was installed and the steps used to make sure it was installed correctly, this is then

                    followed by the steps used to install the front end.

 

                b. Operational Qualification/Performance Qualification: This is the main component of the testing process.

                    When validating a system I develop I do not create separate OQ and PQ scripts,

                    however when validating a COTS system I usually create or use the manufactures

                    OQ and a PQ (see Section D - 4e for a discussion of the OQ and PQ).

 

                    The OQ/PQ It is made up of testing instructions that tests each requirement contained in the

                    requirements document.  Each test should provide the tester with exact instructions,

                    the expected results and a place to indicate if the test was successful or not.  A tester

                    should be able to use the OQ/PQ with little or no assistance.  It is recommended that the

                    test scripts should be numbered to correspond to the system requirements. 

                    The tester should sign and date the OQ/PQ after each functional test grouping.

                    For example, after all testing involving security is completed the tester should sign and

                    date the OQ/PQ.  If a test fails and requires re-testing, a separate test script page should

                     be inserted.  If the test is passed that inserted page should be signed and dated.

                     If you created your own software the OQ/PQ can take a long time to complete.  The

                     more complex the software the longer the OQ/PQ.  Do not underestimate the time and

                     cost of creating the OQ/PQ.

                   

                     I recommend when buying a COTS product see if the manufacture provides or sells

                     test scripts.  This will save a great deal of time and expense.  You may think you will

                     save money by writing your own OQ/PQ instead of buying it, but you will be making an

                     expensive mistake. 

   

                c. Traceability matrix:  This is a spreadsheet or table that maps the requirements to the

                    specific test scripts.  This will serve as an auditor's guide.  Just seeing that you have one

                    will give the auditor confidence in your documentation.  The table feature in Microsoft

                    Word is an excellent tool for creating this matrix.

 

                d.  Test Summary report :  This is the current document being described

 

    3.  Testing Result:  This summarizes the results of the testing.  If you reached this point

         of a real validation package things should have been successful.  You can state that testing is completed

         and the system was shown to pass all tests in the OQ and/or PQ.  Then reference the OQ and/or PQ.

 

    4.  Deviation from Testing Plan:  If there was deviation from the testing plan mention them here. 

         For example, sometimes the OQ tests may not be appropriate.  The test script is found

         during testing to not actually test the requirement. In this case you do not check either

         of the two check boxes, instead you write NA for non-applicable. Then you document

         this in the Derivation section.

 

    5.  Certification of Completion of Testing:  In this section you collect the signatures of individuals

        who certify that testing has been completed and that the Test Summary Report is acceptable. 

        These signatures should include the QC director, a  representative of the user group, person

        responsible for corporate software and a company officer.

 

 

F. Validation Summary Report

The validation summary report provides an overview of all the tasks that one carried out during the validation.

Once again each of the sections listed below should be addressed in the SOP and describe the function of each section.

1.      List the deliverables that were created (i.e. requirements design, IQ, OQ, etc..).  Also mention where these documents are stored.  For example the SOP should mention how you store these deliverables (i.e. all forms are stored  in a locked file cabinet (preferably fireproof), and all the completed documents scanned and stored on a secure network directory (read only)  Reference your SOP on storage of computer media. A word of warning validation is expensive and time consuming, it is not the time to be cheap scan your completed validation package with signatures and as a side note you should also scan all your SOPs). 

2.      COTS documentation.  Here is where you write information about the company from which you purchased the software.  Write the company name, address, phone number, fax number, e-mail address, web page, formal name of the software, serial number of software, version number, salesman's name, location of manuals that accompany the software and any other information you think could be useful.  Remember this information is not for you but it is for the people who follow you.

3.      Names of people and their jobs who participated in the validation.

4.      Overall all result of validation.  State that the validation was successful or if validation was stopped because the software proved to be faulty.

5.      Problems encountered during validation.  During the course of validation if something was not done or if an approval was not obtained, then document it and indicate why the plan was not followed and what was done to compensate for the deviation.  Remember and auditor will not punish you if you admit a problem occurred and you did something to compensate for it, they will write you up if you pretended it did not happen.  You can reference the Testing Summary Report if a deviation in testing is documented there.

6.      Certification that validation has been carried out and the system can be made operational. This is a statement that validation has been completed and that the system can be made operational.  The QC director, person responsible for corporate software, representative of the user group and a corporate officer signs.  These signatures also designate the approval of the validation summary report.

 

 

 

 

 

 

G. Training and Release of System:

 

     These two areas may not be included in an actual validation package but they should be addressed or

      referenced in the validation SOP.     

 

      In your Validation SOP you should mention how you train users when you create or purchase a

      new system.  You should specify who does the initial training (designer of software trains a group

      of sophisticated user who will then be responsible for training other users). Your company may

      have a separate training SOP that can be referenced here.  An important question to address in

      this SOP or in your training SOP is how do you ascertain if a person is adequately trained and

      knows how to use the system.  Do you create a test? Have a trained observer see how they

      operate the system and formally certify them.  It is a good idea to have some documented

      evidence that the users have attained some degree of skill.  This can be done by creating a

      certificate, a training log, etc.  This is evidence of training that can be presented to an auditor. 

     

 

      Document the steps that will be taken to move the system from the test environment to its

      operational environment.  A good procedure is to state you will follow the instructions used in

      the IQ document when moving the system to its operational environment.  Then document this

      by completing a new IQ document with testing results and appropriate signatures to prove

      the move to the operational setting was successful.  This can be included as a deliverable related

      to the Validation Summary Report.

 

 

 

F. Retirement:

The SOP should describe how a system should be retired.  Retirement is usually started by the information technology (IT) department.  A document is drawn up that states:

  

     1. What system is being retired

     2. Why it is being retired

     3. Date of retirement

     4. What if any system will replace this system

     5. How and where the retired system will be stored and where (i.e. tape, in off site storage and

         on site in a secure room)

   

Have the responsible IT person sign and date the form and it should be approved by a QC representative.       

 

 

______________________________________________________________________________________

Last warnings

When you actually validate a system there can be friction between the QC department, the developers and the corporate officers. 

The QC department should not be inflexible and remember that the validation process is created to prove the software works and the end product is a tested system. If there is a good reason not to follow the validation SOP, that is alright as long as you document it and it makes sense.  Finally, get involved with what the programmers and the testers are doing don't sit back and wait until everything is done and then say it isn't good enough..

The developers must remember that if an audit occurs it is the QC staff who will be representing the system and the validation process.  The QC staff have to be satisfied that the documents created will pass an audit because they have to defend them in front of an auditor. There is no worse feeling when an auditor asks for a document and you cannot provide it or you know it is weak.

Corporate officers are shocked at the cost of validation.  However as I mentioned before, if an auditor feels procedures were not followed and writes a warning letter, the cost of correcting the omissions or errors will far exceed the cost of validation.

_______________________________________________________________________________________

If you have any questions please send e-mail to validate@plainsite.net , I am very good at telling people what to do.

Thank you

Val E. Datear PhD.

___Copy written 2006 _________________________________________________________________________

Appendix A

Selected templates:

These are draft templates that you can modify in any way.  These blank templates should be attachments to your Validation SOP.

The Validation Plan

Part 1:

Name of the system and a description of its function

 

 

 

 

 

 Part 2: Risk associated with software that is being validated

Describe the risk inherent in the use of this software

 

Section 3:  Estimated completion time for validation

Start Date:

End Date:

Tasks and estimated completion time:

 

Section 4:  Participants and Tasks

 Participants                       

Tasks for which participant is responsible:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Section 4: Deliverables

Documentation: (List all documentation to be developed to support this system)

 

 

Software: (List main modules or components to be developed for this system)

 

 

 

Section 5: Configuration Management

Code control method:

 

System documentation control method:

 

 

Section 6: Test Approach or Strategy

 

 

 

 

Section 7: Quality Control/Quality Assurance

List software quality activities that will be applied to this project:

Section 8: Technical Training

List all training needed by IT staff to implement software:

 

 

Section 9: Waivers

The validation package will meet the intent of SOP P001, but will not be performed or documented exactly as

specified in the SOP as it is anticipated that this SOP will be retired prior to completion of this project.

Section 10: Signatures

Submitter (System Lead):

 

 

Signature                                                                          Date

QC Reviewer:

 

 

Signature                                                                          Date

Approvers:

 

 

Signature                                                                          Date

User Representative:

 

 

Signature                                                                        Date

IT Director:

 

 

Signature                                                                       Date

QC Director:

 

 

Signature                                                                       Date


 

 

 Test Summary Report

Section 1: Deliverables

 List all deliverables that were created during the testing process

 

Section 2: Description of the Testing Environment

 Describe the hardware and software of the testing environment (i.e. servers, operating system, database used [Oracle, MS SQL server, My SQL, etc..])

 

Section 3: Test Results

 This should refer to the completed operational testing script.

 

 

Section 5:  Appraisal of testing

Was the testing successful

 

Section 6:  Problems that arose during testing

 

 

 

Section 7: Certification – Approval of testing activities

 

 

QC Representative

 

 

Signature                                                                               Date

 

QC Reviewer

 

 

Signature                                                                               Date

 

Corporate Officer:

 

 

Signature                                                                               Date

 

 

 

 

Signature                                                                              Date

 

 

Validation Summary Report 

Section 1: Actual Tasks Timeline

This section documents the tasks and the actual time it took to complete them

 

Start Date:

End Date:

Tasks Performed:

 

 

Section 2: Documents generated during validation process

List all the documents generated during the validation process 

 

 

 

Section 3:  Vendor Information

 List the names, addresses, phone numbers, e-mail addresses of the manufacturers whose software was used to create the system.  If it is a COTS product the information on the primary manufacturer should be entered here.

 

 

Section 4: Training

 

 

Section 5: Actual Participants and tasks that were performed 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


 

Section 6: Deviations from the Validation Plan

 

 

 

 

 

 

Section 7:  Certification for deployment

Final certification verifying that all validation processes were carried out successfully

 

QC Representative

 

 

Signature                                                                               Date

 

QC Reviewer:

 

 

Signature                                                                               Date

 

Corporate Officer

 

 

Signature                                                                               Date

 

 

 

 

Signature                                                                               Date

 

Deviation Report Form

 

System :______________________                                                               Date ____________________

Problem encountered:  _____________________________________________________________________

_______________________________________________________________________________________

_____________________________________________________________________________

 

Will the requirement document need to be modified     Y__   N___

What Deviation was carried out __________________________________________________________

___________________________________________________________________________________

___________________________________________________________________________________

___________________________________________________________________________________

 

 

Justification for carrying out the deviation _________________________________________________

_________________________________________________________________________________

_________________________________________________________________________________

_________________________________________________________________________________

 

 

Approval:

 

Deviation Approved?         _____ YES   _____NO

Approval Signatures

QC Director _____________________________________________________   Date ___________

Programmer _____________________________________________________   Date ___________

QC Reviewer ____________________________________________________  Date ___________

 

 

 

Documents generated during Validation (List how and where they are stored)

Validation Plan
Requirements Document

Detailed Systems Design

Installation Qualification (IQ)

Operational Qualification (OQ)/Performance Qualifications (PQ)

Traceability Matrix

Test Summary

Validation Summary Report

Error Log

User Manual

Training Documentation

System Retirement Form